| Project Number (JTEG Assigned) | NA-09-0007 |
| Project Title | SPEC-EDM drill |
| Service | NAVAIR |
| Command | NORIS |
| Implementation Depot | NORIS |
| Project Lead | Alcide Richards 619-545-3171 |
| TI Goals Supported | Performance, schedule, cost |
| Focus Area | Metal Working |
| Platform General | Aircraft |
| Platform Specific | |
| Implemented Technology | Electro Discharge Drill |
| Problem Definition | Hard (titanium) fasteners are hard to remove |
| Proposed Solution | Implement the EDC drill as approved fastener removal. |
| Expected Result | Improved depot process modeling software. |
| Benefits | Less damage to surrounding area when fastener removed. |
| Unfunded Requirement | No |
| Start FY | FY09 |
| Completion Date | |
| WIP | Yes |
| Implemented | No |
| Comments | On schedule for demonstration end of June |