Project Number (JTEG Assigned) | MC-09-0006 |
Project Title | Renewable Energy |
Service | Marine Corps |
Command | LOGCOM |
Implementation Depot | Barstow |
Project Lead | Greg Russell (229) 639-8072 gregory.russell.ctr@usmc.mil |
TI Goals Supported | P-1, C-2, S-3 |
Focus Area | Environmental |
Platform General | Other |
Platform Specific | All workloads. |
Implemented Technology | Alternative energy generating equipment. |
Problem Definition | Comply with EO 13423 on the guidelines to increase the use of renewable energy sources. |
Proposed Solution | Various initiatives are currently underway: use of methane landfill gas in MCA and wind turbines at MCB. |
Expected Result | Reduction of energy intensity. |
Benefits | Reduce the energy intensity of depot operations and provide a source of renewable energy. |
Unfunded Requirement | No |
Start FY | FY09 |
Completion Date | |
WIP | Yes |
Implemented | No |
Comments | Expect this project to continue for years. |